Dear Residents, Family and Friends,
I am pleased to advise we have managed to get some traction with our build program over the last couple of
weeks, with a number of sunny days! Most notably, the Eastern main slab area has now been fully
poured/completed. The Maintenance Shed slab on the North Eastern end will be poured within the next few
days.
On the western side, in ground plumbing work continues – which we expect should be completed by next week.
Demolition of existing paths and patios is underway. New concrete patios and pathways will be established
within the next few weeks for the internal western courtyard.
Looking ahead, demolition work will begin behind the main kitchen area, to prepare for works to begin on the
extension there.
Next week further work on the Eastern end will be undertaken to establish stormwater in-ground infrastructure
now the main slab is established.
Also we expect towards the end of next week, work to begin on forming up for the main western slab end.
A little further ahead, framing we expect to arrive and commence around Mid July.
We continue to look forward to these works progressing, and ultimately delivering new spaces for our residents
to enjoy and live in, here at BlueWave.
Yours sincerely,
Matt Downie
CEO